On Tuesday, August 24, 2021 Charleston County Council voted 9-0 to move the Compromise Alternative forward through the environmental review process and further into design. Since the project kicked off in 2017, the Charleston County project team has diligently followed a rigorous environmental review process, which included extensive public involvement and a detailed alternatives evaluation to examine environmental, social, cultural, and economic impacts of the proposed project. The process has worked, and the project team was able to identify a Compromise Alternative that is reflective of the needs of surrounding communities while also managing the growing traffic congestion along Highway 41.
The Compromise Alternative consists of two travel lanes in each direction from the Wando River Bridge to Dunes West Boulevard/Rivertowne Parkway, one lane in each direction with a center turn lane/median through Phillips Community, two travel lanes in each direction from south of Joe Rouse Road to Highway 17, and adds a two lane southern parkway from Highway 41 to Park West Boulevard along the edge of Laurel Hill County Park. The Compromise Alternative also includes changes from earlier alternatives to reduce right-of-way impacts at the Highway 17 intersections with Highway 41 and Winnowing Way.
This Compromise Alternative was originally presented to Charleston County Finance Committee on August 5, 2021 and a link to the presentation is located here.
The project team is committed to continuing to work closely with surrounding communities and stakeholders as the project design, Environmental Report, U.S. Army Corps of Engineers (USACE) permit application, and the South Carolina Department of Environmental Services (SCDES) permit application are being reviewed.
Charleston County submitted permit applications and supporting documentation to the USACE in May 2023 and SCDES in December 2023. As of June 2025, the project design has been updated to further minimize impacts to wetlands and critical areas. Therefore, the permit applications, Environmental Report and supporting documentation were updated to reflect the reduction in impacts and were resubmitted to the USACE and SCDES.
Updated versions of the Environmental Report and Supporting Documentation may be viewed here, and more information can be found at USACE - SC 41 Corridor Improvements Charleston County, South Carolina.
You can view the current Highway 41 project map here and the project schedule below.
Dates are approximate
Public Meetings - November 2017 and May 2018
Virtual Public Meeting for the Proposed Alternative - August 2020
Presentation of Revised Concept - March 2021
Compromise Alternative Presented - August 2021
Develop Preliminary Alternatives - Spring 2018
Develop/Refine Reasonable Alternatives - Spring 2018 to Fall 2020
Traffic Studies - Spring 2018 to Fall 2020
Public Comment and Development of Revised Concept - Late 2019
Identify Proposed Alternative - June to August 2020
Develop Conceptual Plans - Throughout 2021
Update Environmental Studies and Environmental Report - Mid 2021 to Early 2023
Submit Permit Application and Environmental Report to USACE - Mid 2023
USACE 30-day public notice and comment period - Fall 2023
USACE Review and Estimated Permit Issuance - Spring 2023 to Spring 2025
Right of Way Development - Fall 2023 to Early 2025
FInal Design and Right-of-Way Acquisition - Early 2025 to Fall 2026
Construction - 2026 to 2030